Procurement Cycles for Designers & Vendors

For IU Health New Downtown Hospital in Indianapolis

The IU Health Design & Construction team for the IU Health new downtown hospital campus will start reviewing and hiring vendors for designing and building on the following schedule.

Procurement Cycle Schedule

Project Name Construction Cost Forecast Start & End ConstructionDesigner
New Hospital/Clinics

$1.97 billion
Wilhelm/Gilbane

Q1 2022 - Q3 2027 Curis Design (BSA, CSO & Ratio)
South Support Building $162 million
Garmong
Q2 2023 - Q4 2025 Lamar Johnson Collaborative
Central Utility Plant $175 million
Weddle Brothers
Q2 2023 - Q3 2025 Applied Engineering
Capitol View
MOB & Garage
$132 million
Meyer Najem
Q4 2021 - Q4 2026 atlierRISTING for Core and Shell and parking grages

TI Design TBD
Site Utilities, Hardscape & Landscape $140 million
Harmon/Walsh
Q3 2023 - Q4 2027 VS Engineering

Designers and construction managers who would like to be directly contracted with IU Health need to be registered as a vendor and prequalified. Please visit the vendor relations page for more registration information. For questions about prequalification, please contact: iuhdesignandconstruct@iuhealth.org.